Ashburton Water Treatment Upgrades
Client:
Ashburton District Council
Consultant:
Beca
Contract:
$4,500,000.00
Duration:
August 2024 – February 2026
Services:
Civil Engineering
Mechanical
Fitout + Installation & Commissioning of new UV reactors
Construction of new buildings to house new pipework and treatment equipment.
Project Management
Brief:
This project was spread across 5 water treatment plants around the Ashburton District. Each site required new UV disinfection of drinking water supplies, along with filtration and PH correction (where required).
Scope:
- Earthworks to extend plant areas.
- Construction of new block buildings to house UV equipment.
- Supply & install new stainless pipework and mechanical fittings.
- Raw water supply cut-ins and re-aligning pipework.
- Installation of new switchboards and electrical equipment.
- Relocation of water analysers and commissioning.
- Water shutdowns and planning cut-ins.
- Recommissioning of supplies.
- Reinstatement works.