Ravenswood Stage 6a WWPS and Culvert

Client:

Ravenswood Developments Ltd

Consultant:

Davis Ogilvie

Contract:

$1,400,000

Duration:

August 2023 – December 2023

Services:

Civil Engineering
Mechanical

Precast and Insitu Concrete

Project Management

Brief:

Construction of a new wastewater pump station for Stage 6a of the residential development, along with a new access culvert consisting of twin DN1950mm pipelines.

Scope:

Pump Station

- Temporary works consisting of a cofferdam 8m x 4.5m with 9m deep FSPIII sheet piles to allow excavation to 5m deep.

- Bulk excavation to foundation RL’s.

- Installation of 12m long screw piles.

- Insitu concrete foundation slab below wet well.

- Installation of precast wetwell, valve and flow meter chambers including ass pipework and mechanical fitout. 

- Yard construction - wash down pad, fencing and pavement works.

Culvert

- Existing stream diversion.

- Overseeing bulk excavation.

- Dewatering management.

- Raft construction.

- Installation of 16x DN1950mm concrete pipes.

- Install precast settlement slabs and precast headwall panels.

- Geogrid tiebacks and backfilling.

- Road formation, kerb lines and footpath construction.

- Management of stone facing and capping.

- Installation of concrete pillars and steel balustrade panels.