Waikuku Beach Headworks Upgrade
Client:
Waimakariri District Council
Consultant:
Waimakariri District Council
Contract:
$550,000
Duration:
November 2018 - February 2019
Services:
Civil Engineering
Electrical
Mechanical
Precast and Insitu Concrete
Project Management
Brief:
Upgrading of the existing Waikuku Beach water supply headworks on Kings Ave inculding building extension and pipework/treatments upgrades.
Scope:
-Temporary bypass of the existing headworks to allow the upgrade to progress.
-New and upgraded pipe works to and from the headworks.
-Extension of the existing headworks building including foundation slab, blockwork and roofing.
-Installation of new and upgrade of electrical controls.
-Supply and installation of a UV reactor for treatment of the bore water.
-Design supply and installation of chlorine dosing to the bore water.
-Testing and commissioning of all the electrical, mechanical and treatment works.